Blade mover – a flexible dual transport system

The two elements of the blade mover

One of the many problems posed by the huge wind turbine blades currently in the market is how to move them quickly and safely.

In some situations (like in the factories, or when blades are temporarily stored before installation) space can be extremely limited and there is the risk of damages. Additionally manipulating and moving the blades can be a time consuming activity.

To solve this problem a Danish company (SH Group) has developed an interesting solution, currently used by a blades manufacturer.

The “Blade Mover” uses two elements, one at the root of the blade (a trailer pulled by a vehicle) and the other at the tip, where a self-propelled vehicle with a diesel engine is driven by a technician using a remote control.

The vehicle at the tip is extremely manoeuvrable, allowing full control on the steering wheels – you can basically orientate the wheels in every direction you may need.

The tip element - an independent vehicle

The system has been develop to carry blades with a weight up to 80 Ton.

I also see from the pictures and the YouTube videos that it use custom frames. The frames are connected to the blade mover using a flexible sliding mechanism with safety pins.

The tip frame. All components can be modified to fit a specific blade

One additional benefit of this system is that it can work on uneven terrains absorbing height differences with a hydraulic mechanism.

The blade mover in action. The technician is using a remote control system.

 

BoP vs. BoS - similarities and differences

Lately I have had the pleasure to spend a lot of time with my friend Alessandro.

Alessandro is an engineer specialized in the design and construction of photovoltaic plants – basically, a "solar energy" version of mine.

We spent some time discussing similarities and differences in the BoP (“Balance of Plant”) of wind farms and the BoS (“Balance of System”) of photovoltaic plants.

As you are reading this blog you will probably know that BoP and BoS basically mean “everything but the wind turbines (or the panels, in the case of BoS)”

Both can have quite an impact on the economics of the project. For wind farm is usually in the 20% to 30% range of the CAPEX while for solar plants it is typically much more – even above 50% of the investment total.

I have made a quick number with some projects currently under development in Southern Italy and I see that for medium size projects (10 to 20 MW) the cost of the modules is only 40%.

This could sound counterintuitive but is a consequence of the unstoppable reduction of the price of the solar modules. At the current rate the price is decreasing 75% every 10 years and this trend does not seem to change.

As a consequence, the BoS becomes every year more relevant (because it is not decreasing at the same rate, so its relative weight keep increasing).

Let's take a look at similarities and differences between BoP and BoS.

In both cases you will need internal roads and probably a substation to connect to the grid (unless the project is very small – for projects of few MW sometimes it is possible to connect directly to the grid in medium voltage).

Additionally, sometime the panels have a shallow foundation (“ballast”) that reminds somehow the shallow foundation of wind turbines on a much smaller scale.

Furthermore the engineering works to be done (geotechnical survey, topography, electrical and civil design, etc.) are very similar.

And this is more or less where the similarities end.

The differences are much more remarkable. For instance, a substantial amount of the BoS budget comes from the support structure of the panels, inverters and trackers.

Inverters are the elements that convert the electricity produced by the solar modules for DC to AC

Trackers are used to rotate the panels in order to have them always in the best position to maximize energy production. They are optional, but they are used frequently because they are generally a cost effective technology.

It is also very unlikely that you will see a solar plant on a steep terrain (with a strong inclination), while this situation is frequent in wind farms (many of them are placed on mountain ridges).

This happen because there is a limit to the height difference that can be absorbed changing the length of the elements that sustain the panels. Additionally, excessive height differences can make the work of the trackers more burdensome with an increased risk of failures.

For these reasons the usual maximum slope in a solar plant is usually around 5% or 6% - and therefore earthworks are limited and less expensive (at least compared to some projects that I have seen on top of mountains where a lot of blasting was needed).

For the foundations I mentioned before the shallow “ballasted” solution. This is basically a block of concrete holding the modules in place.

However the use of piles is usually more cost effective. Several alternatives are available depending on the geotechnical characteristics of the soil (helical piles where cohesion is low, driven piles when the soil is more dense, etc.) and in addition to the monetary advantage they are also usually faster to install and easier to decommission at the end of the life of the project.