Wind site assessment

The wind site assessment (or “wind and site” assessment) is one of the most important steps in the development of a wind farm.

Basically is a in depth analysis of the site conditions of the area where a wind farm could be built.

Purpose of this assessment is calculate energy production and suitability of a specific WTG model to the local conditions.

Such study is usually performed by different stakeholders – external consultancies (possibly on behalf of financial institutions), wind turbines manufacturers and even developers (if they are big enough to have a wind & site department in house).

The inputs for the site assessment are:

  • Wind data
  • Topography & Roughness conditions
  • Other environmental conditions

Wind data includes usually raw data from one or more met masts. Measurement period should be sufficiently long, ideally several years. Key data are the wind rose (from where the wind is blowing), the distribution of the wind speeds (it follows a Weibull distribution) and the normal and extreme wind speeds.

Topography & Roughness conditions have an impact on turbulence, flow inclination and local speed up effects that can be key in the selection of the correct wind turbine.

Other environmental conditions include parameters such as temperature (both very high and very low temperature will need a special “package” and usually leads to decreased energy production), air density (will change the loads, and if very high or low could lead to a derating) and seismic actions (will the tower withstand earthquakes?).

All this data is cross checked against standard wind classes. These classes have been defined by the IEC, an international committee of experts, and are often used to categorize a wind turbine model. For instance, wind turbine A could be certified for wind class I (strong wind) while wind turbine II could be certified for wind class III (weak wind).

It’s important to highlight that usually there is uncertainty on one or more parameters. Therefore different assumptions are made by the wind & site engineers. The interesting part of the story is that, depending on where you are working, you will be interested in “twisting a bit” the numbers in a different direction.

For instance, an external consultant will usually be more conservative when analysing energy production (as he doesn’t want to be blamed if the actual production is lower).

Conversely, a WTG manufacturer could possibly give you higher number when calculating energy production. This is good for 2 reasons: because more production means more money for the prospective customer, and because considering higher loads put the engineer on the safe side when assessing expected life of the key components of the wind turbine.

One response to “Wind site assessment”

  1. mohammad Avatar

    this is a great information

Leave a Reply

Your email address will not be published. Required fields are marked *