Wind farm projects management guide: what to do and when

A wind farm development is usually a complex, collective effort where several different companies are involved – the developer, the financing institutions,  the WTGs manufacturer, the companies doing the BoP and installation and several other.

As many tasks are performed in parallel, often is not very clear to people who are not in the wind industry who is doing what and where.

Luckily, my friend Alberto from ACWA sent me this enlightening step by step guide. It has been developed by K2, a management company active in the business.

As you might imagine sometime the borders between activities are sometime blurry and some task might be shuffled. For instance, the environmental impact study in some countries is done very late (you will probably have to work only with some preliminary document), or the land lease agreement can be closed very late in time. We’ve been forced to relocate quite a few turbines in projects ready for construction where landowners where very reluctant to close a deal.

Also, as I’m obsessed with engineering and construction, I do disagree with the construction line, where  the “Balance of Plant Completed” comes in parallel (and terminates before) with the “Detailed Design Complete”. The implication of this structure is that you could start construction without having construction drawings, which is usually not a good idea )although is something that I see recurrently).

However the scheme is very instructive – I hope you will find it useful for your business.

This entry was posted in Turn Key Wind Farms and tagged , , by Francesco Miceli. Bookmark the permalink.

About Francesco Miceli

Hello!My name is Francesco and I'm a civil engineer specialized in EPC (that is, "turnkey") wind farms projects.I'm currently based in Hamburg, Germany and I'm developing several interesting project all around the world - southern Europe, LATAM and various other countries.If you want to contact me please don't leave a comment in the blog (I don't check them very often) - you can use the contact form.You can write me in English, Spanish and Italian.To find a (somewhat concise) description of my non-wind business activities you can visit my webpage - www.francescomiceli.comIf you want to know more about my work, here you can download my CV - www.windfarmbop.com/CV_Francesco_Miceli.pdfHope you like the blog!Francesco

3 thoughts on “Wind farm projects management guide: what to do and when

    • Hello Richard,
      the energy is transferred using medium voltage cables.
      Normally they are buried in trenches but sometime overhead lines are used.
      There are different possible voltage levels. The final choice depends on several technical and economic considerations.
      Ciao, Francesco